by Nathan Simmons
388th Fighter Wing
9/24/2014 - HILL AIR FORCE BASE, Utah -- Aggressive
renovation and modification is in full swing at Hill Air Force Base in
preparation for the military's newest multi-role fighter aircraft.
Hill's preparations for the F-35A, total more than $100 million, with 23
projects to be completed between now and July 2015. Thirty-six total
projects will be finished once construction concludes in 2019.
Hill's 388th Fighter Wing and the Air Force Reserve 419th Fighter Wing
will become the Air Force's first operational units flying the F-35A,
with the first jet projected to arrive in September 2015. The 388th
became the first fully-operational F-16 Fighter Wing in 1979, and was
the first unit to fly the F-16 into conflict with the Low Altitude
Navigation and Targeting Infrared for Night system through the skies of
Iraq and Kuwait during Operations Desert Shield and Desert Storm.
Earlier this month, F-35 Joint Strike Fighter program leader Lt. Gen.
Christopher Bogdan warned there is danger of missing deadlines if F-35
jets aren't flying regularly by the end of September.
"I need all of [the test airplanes] back to full envelope by the end of
this month," Bogdan said at a recent conference in Washington.
"Otherwise we will start seeing some delays in future milestones."
Col. Lance Landrum, 388th Fighter Wing commander, said the challenges
the F-35 program is facing aren't affecting how the 388th is preparing
for the new fighter's arrival.
"We're currently in the most invasive phase of the construction, and our
mission hasn't slowed down at all in the process - we're still flying
as many sorties as we can, maintaining our fleet of F-16s, and staying
combat ready all while making huge adjustments in preparation for the
F-35," Landrum said.
The 388th FW is scheduled to receive 72 F-35A jets total. The wing will
get an initial cadre of pilots from the F-35 test and training units at
Eglin AFB, Fla., Luke AFB, Ariz., and Nellis AFB, Nev., while also
gaining F-35 qualified pilots from other fighter wings, and retraining
some F-16 pilots currently in-house.
Hill will likely receive 83 F-35 qualified maintainers by December 2015
and transition more than 100 legacy technicians to F-35 maintainers
within the first year of operations. Team Hill collectively will gain
roughly 475 members, both active duty and civilian during the transition
to the F-35.
The timeline to renovate facilities has been compressed significantly,
as the start time to base the jet was pushed back by the delayed record
of decision. However, base officials have full faith that Hill will be
ready for the F-35, when the base receives the first jet in September
2015.
"We're confident the construction will be on time for the first aircraft
arrival, even with our late start after the record of decision was
made," said Ron Stonebreaker, chief of design and construction
management in Hill's civil engineering sector.
Stonebreaker said the projects aren't steady state - there is constant
evolution in preparing for the F-35. His team developed a floor plan for
one major hangar that will house the aircraft maintenance units, but
then learned there were special requirements for communications rooms -
connectivity between the maintenance and operations teams built around
the new jet's automatic logistics information system, which ties those
two functions together. His team had to modify the contract and adjust
the floor plan to accommodate that requirement.
F-35 sustainment is already in place at Hill's Ogden Air Logistics
Complex; the ALC is currently converting dock space used to modify the
F-16 to depot maintenance space for F-35. Stonebreaker said post
production modifications will likely be a critically important
component, as the aircraft is still in development. The Ogden ALC
completed the Air Force's first organic depot modifications on an F-35
earlier this year.