from Secretary of the Air Force Public Affairs
9/5/2013 - WASHINGTON (AFNS) -- The
Air Force officially closed the KC-46 Weapon System Critical Design
Review (CDR) on August 21, one month ahead of the Sept. 24 contractual
date.
This formal closure of the July Weapon System Design Review represents
the culmination of more than 10 months of component and sub-system
design reviews, resolution of all resulting action items and completion
of all CDR criteria established in the Air Force's contract with Boeing.
Closure of CDR formally establishes the KC-46 design and now allows the
program to progress into its manufacturing and development test phases.
The KC-46 is based on the Boeing 767-200ER commercial aircraft. Design
review activities blended best practices of commercial and Department of
Defense frameworks, leading to overall improvements.
Boeing will now proceed with integration, verification, and production
of four engineering and manufacturing development aircraft to support
flight testing, scheduled to begin in mid-2014. The first fully equipped
KC-46 tanker is projected to fly in early 2015.
"This build and test phase is another critical step toward meeting the
KC-46 contractual Required Assets Available date -- a milestone
requiring 18 KC-46 aircraft and all necessary support to be on the ramp,
ready to support warfighter needs by the August 2017 timeframe," said
Maj. Gen. John Thompson, Air Force program executive officer for
tankers. "To succeed will require the focused efforts from all members
of the team."
The Air Force contracted with Boeing in February 2011 to acquire 179
KC-46 refueling tankers to begin recapitalizing the more than 50-year
old KC-135 fleet. Production will ramp up to deliver 179 tankers by
2028.