by Jet Fabara
412th Test Wing Public Affairs
5/8/2013 - EDWARDS AIR FORCE BASE, Calif. -- In
2006, the C-5 Galaxy underwent a "super" upgrade to further strengthen
the airframe's worldwide airlift capabilities. Test teams here and at
Dover Air Force Base, Del., are showing why the recent software upgrade
to the largest aircraft in the Air Force inventory -- now known as the
C-5M Super Galaxy -- is no small task.
With initial modifications being tested at Dover AFB, the aircraft has
been ferried back to Edwards AFB where the remaining flight test sorties
are being accomplished during May.
"The C-5M Super Galaxy Block 3.5.2 software upgrade is intended to
correct 72 deficiency reports that were documented during previous C-5M
test programs," said Joel Williams, 775th Test Squadron C-5 lead
engineer at the 418th Flight Test Squadron.
"The results of the 418 FLTS testing of 3.5.2 will help support a
fielding decision by the program office at Wright Patterson Air Force
Base, Ohio," added Maj. Zackary Schaffer, 418 FLTS C-5 test pilot.
"Additionally, data from this testing will be used by the Development
System Manager at the Air Force Life Cycle Management Center at
Wright-Patt to generate a program assessment summary to verify the C-5M
retains the navigational performance and surveillance capabilities
necessary for future airspace requirements."
According to the C-5M test team, the systems affected by this software
upgrade included the automatic flight control system, auto throttle,
display services, embedded diagnostic system and flight management
system.
"As part of the Traffic Collision and Avoidance System testing, we had
to develop test techniques to safely generate collision warnings
in-flight," Schaffer said. "With the help of pilots at the 445th Flight
Test Squadron and the Massachusetts Institute of Technology's Lincoln
Laboratory, we were able to develop procedures using a T-38 Talon to
generate all of the appropriate warnings while ensuring safe separation
of aircraft throughout the test."
Initially, the aircraft was modified with test instrumentation and
software at Dover AFB, which required all of the checkouts, Quality
Assurance inspections and initial ground and flight testing to be
conducted off-site.
"Thanks to the excellent coordination between Edwards Special
Instrumentation team, Lockheed Martin Aeronautics, and the 436th
Maintenance Group, all the modifications were completed ahead of
schedule with the airplane fully mission capable," said Schaffer. "With
help from the 436th Operations Group, we were able to schedule all of
the range support necessary for our testing."
Once the final portion of software upgrade testing is completed,
Williams said the DR corrections will help bring many improvements to
the C-5M platform including a new vertical guidance mode, new glideslope
capture capabilities, identify friend or foe mode S enhanced
surveillance, and updated traffic collision and avoidance logic.
The C-5 Development System Manager, AFLCMC/WLS at Wright-Patterson AFB,
will use the result of testing to support airworthiness certification of
the software update. The testing results will also support
certification of readiness for operational testing that will be
conducted by the Air Mobility Command Test and Evaluation Squadron.
C-5M Block 3.5.2 software upgrade testing is projected to be completed
by the end of May 2013. The Air Force plans to upgrade 52 Galaxies to
"super" status by the end of 2016.
Friday, May 10, 2013
Subscribe to:
Post Comments (Atom)
No comments: